After the press box at Beaver Stadium was demolished in January in front of hundreds of onlookers, work on the west side of the stadium continues as part of a larger renovation project.
As the major project nears the end of its fourth month, beams have been installed while work on the $700 million project continues.
Plans for the full project, which received final approval from College Township in October, will provide new restrooms, upgraded concessions and seating, improved field lighting, a renovated press box and the construction of a new welcome center at Beaver Stadium. Other site work, including hardscape replacement, will help improve circulation and alleviate congestion on stadium concourses and exterior plazas.
Below, we’ll share weekly photos of the project.
Wednesday, April 23
Construction on the west side of Beaver Stadium on Wednesday, April 23, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, April 23, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, April 23, 2025. Abby Drey adrey@centredaily.com
Wednesday, April 16
Construction on the west side of Beaver Stadium on Wednesday, April 16, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, April 16, 2025. Abby Drey adrey@centredaily.com
Wednesday, April 9
Construction on the west side of Beaver Stadium on Wednesday, April 9, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, April 9, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, April 9, 2025. Abby Drey adrey@centredaily.com
Wednesday, April 2
A large crane is on site as construction on the west side of Beaver Stadium continues on Wednesday, April 2, 2025. Abby Drey adrey@centredaily.com
New beams are being installed as construction on the west side of Beaver Stadium continues on Wednesday, April 2, 2025. Abby Drey adrey@centredaily.com
A large crane is on site as construction on the west side of Beaver Stadium continues on Wednesday, April 2, 2025. Abby Drey adrey@centredaily.com
New beams are being installed as construction on the west side of Beaver Stadium continues on Wednesday, April 2, 2025. Abby Drey adrey@centredaily.com
New beams are being installed as construction on the west side of Beaver Stadium continues on Wednesday, April 2, 2025. Abby Drey adrey@centredaily.com
Wednesday, March 26
Construction on the west side of Beaver Stadium on Wednesday, March 26, 2025. Abby Drey adrey@centredaily.com
The suites at Beaver Stadium are visible as construction on the west side the stadium is underway on Wednesday, March 26, 2025. Abby Drey adrey@centredaily.com
Wednesday, March 19
Construction on the west side of Beaver Stadium on Wednesday, March 19, 2025. Abby Drey adrey@centredaily.com
Wednesday, March 12
Construction on the west side of Beaver Stadium on Wednesday, March, 12, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, March, 12, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, March, 12, 2025. Abby Drey adrey@centredaily.com
Wednesday, March 5
Construction at Beaver Stadium continues on Wednesday, March 5, 2025. Jessica McAllister jmcallister@centredaily.com
Construction at Beaver Stadium continues on Wednesday, March 5, 2025. Jessica McAllister jmcallister@centredaily.com
Tuesday, Feb. 25
Construction crews work on the west side of Beaver Stadium on Tuesday, Feb. 25, 2025. Abby Drey adrey@centredaily.com
Construction crews work on the west side of Beaver Stadium on Tuesday, Feb. 25, 2025. Abby Drey adrey@centredaily.com
Wednesday, Feb. 19
Construction on the west side of Beaver Stadium on Wednesday, February. 19, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, February. 19, 2025. Abby Drey adrey@centredaily.com
Wednesday, Feb. 12
Construction on the west side of Beaver Stadium on Wednesday, Feb. 12, 2025. Abby Drey adrey@centredaily.com
Construction on the west side of Beaver Stadium on Wednesday, Feb. 12, 2025. Abby Drey adrey@centredaily.com
Wednesday, Feb. 5
Construction on the west side of Beaver Stadium on Wednesday, Feb. 5, 2025. Abby Drey adrey@centredaily.com
Construction crews work on the west side of Beaver Stadium on Wednesday, Feb. 5, 2025. Abby Drey adrey@centredaily.com
Wednesday, Jan. 29
Construction at Beaver Stadium on Wednesday, Jan. 29, 2025. Abby Drey adrey@centredaily.com
Wednesday, Jan. 22
Crews work on the west side of Beaver Stadium on Wednesday, Jan. 22, 2025. Abby Drey adrey@centredaily.com
Crews work on the west side of Beaver Stadium on Wednesday, Jan. 22, 2025. Abby Drey adrey@centredaily.com
Wednesday, Jan. 15
The upper west side of Beaver Stadium been demolished and crews work at the site on Wednesday, Jan. 15, 2025. Abby Drey adrey@centredaily.com
A look at Beaver Stadium with the upper west side and press box demolished on Wednesday, Jan. 15, 2025. In the foreground crews work on the Jeffrey Field Soccer Complex and Indoor Practice Bubble. Abby Drey adrey@centredaily.com
Wednesday, Jan. 8
Crews work in the snow on the demolition of the west side of Beaver Stadium on Wednesday, Jan. 8, 2025. Abby Drey adrey@centredaily.com
Crews work in the snow on the demolition of the west side of Beaver Stadium on Wednesday, Jan. 8, 2025. Abby Drey adrey@centredaily.com
This story was originally published January 8, 2025 at 3:01 PM.